Issue No. 357

23 - 29 August 2001

Project overview

Alec A. Mizzi, CEO of the Alf Mizzi & Sons Group and director of Midi plc, talks to Blanche Gatt about progress on the Manoel Island and Tigne Point project

Almost 10 years after negotiations over the Manoel Island and Tigne Point site began, the MIDI Consortium finally declared the project open last December. Despite the years of debate and controversy, it was only a year ago, in June 2000, that the formal agreement ceding the land to the consortium was signed. But, as the old saying goes, good things come to those who wait – and the MIDI Consortium has certainly done its fair share of waiting.
Composed of 11 shareholders, the Consortium has committed to a project that encompasses 44 hectares of land and will cost Lm140m to develop. With a target date of 12 years for total completion, the entire project, that will cover 34 per cent of Tigne Point and 80 per cent of Manoel Island, as well as a 350- berth marine and a breakwater, will eventually grow to include 940 residential spaces, 10,100 square metres of office space, retail outlets, catering facilities, a casino, a 300-room five-star hotel and 17,238 sq. metres of sports and leisure facilities, as well as over 3,000 underground parking spaces.
As the first, preparatory phases of the project get underway, I went to speak to Alec Mizzi, CEO of the Alf Mizzi & Sons Group, and a member of the consortium, to find out how the shareholders are feeling about the progress on their massive
investment.
The long drawn out negotiations with government spanned three different legislatures, and involved a constantly-changing stream of ministers, officials and negotiators on the government side. “I think it was 1992 when the whole thing started,” Alec said. “The negotiations were long and complicated – especially because first we were dealing with a Nationalist government, than a Labour one, and then Nationalist again. So until agreement was reached a year ago on 15 June 2000, it was a pretty long road to travel. Fortunately we always dealt with positive negotiators and are pleased to note that all successive governments supported the project.”
A strong commitment to the project was essential to maintain the momentum despite the obstacles. “This project was different – on such a large scale – that it was very attractive to us,” explained Alec. “We always believed there was an excellent business opportunity in the project, but also that it was the kind of endeavour that would actually make a difference. So it was worth pursuing. And in fact, through the negotiations, for the last six to seven years, we already had whole teams of people, including architects and designers working on the outline plans of the project, as well as financial and legal consultants.”
However, despite the fact that work has started at last, and the two architects, Alex Torpiano and Conrad Buhagiar and their teams, are now busily filling in the outline drawing with detail that must all still be passed by the Planning Author-ity, there also remain a few outstanding problems. “Part of our contract is to carry out infrastructural work like improving the access to Manoel Island, for example,” Alec said. “The new road will be built at government expense, but with us as the project managers. However, it has not yet been dec-ided how exactly to go about it. There are a number of options, one of which involves the demolition of a number of houses, but this has not been decided yet.”
Alf Mizzi & Sons Group is one of the three largest shareholders in the consortium, with 15 per cent of the total shares. As they watched the years fritter away into interminable discussion and counter discussion, how did they feel about this significant investment?
“Well, there’s no doubt this was nine years of wasted time,” replied Alec. “It started and stopped,
started and stopped, over and over again. We originally thought the negotiations would be concluded within a year or two, but it dragged on so long. Throughout this time, we considered pulling out several times. There were moments when we were very frustrated and thought that’s it, we’ve had enough. But we had already made a substantial investment of over a million liri before we even signed the agreement, and we had even carried out numerous impact assessment studies for the Planning Authority, so pulling out would have meant throwing all that work away. And, fundamentally, we always believed in the project, and we always had a broad agreement on the fact that it was an attractive project, despite the frustrations.”
The frustrations, as we all remember included the problem of what to do with current occupants of the site. While a number of the tenants on Manoel Island and Tigne Point were offered alternatives which they accepted with no fuss, a few of the residents at Tigne Point caused an uncomfortable sticking point. “Of course,” explained Alec, “we have no relationship with any of these people. Their relationship is with government. But there is no doubt that this was one of the reasons for the delays that beset us, both in Tigne and Manoel Island. However government knew we were not prepared to take on the project without vacant possession of the site, so this had to be sorted out. Arrangements have now been settled, however, some of them with our help. The Sliema football pitch is going to be rebuilt above the shopping centre, as is the Gzira pitch. For the nine outstanding residents at Tigne Point, we shall be incorporating specially built maisonettes for them within the development. This was a compromise – not ideal, but at least allowed us to move on.”
Was compromise the only sort of help the consortium offered? “We didn’t pay any money to anybody to get vacant possession,” said Alec. “But we helped in that we acceded to some of the requests, even if they were inconvenient to us. Basically we couldn’t do otherwise, or the project would have been stalled even longer than it was.”
In fact, the massive project is going to transform the two areas that have for years lain derelict and abandoned to the twin ravages of human vandalism and the elements. Incorporating the restoration of valuable historical buildings such as Fort Manoel and Fort Tigne, Lazzaretto Hospital and Tigne Barracks, the work carried out is going to be a delicate process which will involve careful supervision from specialist conservationists like Fondazzjoni Wirt Artna.
“Part of our obligations are to restore the Forts to their former pristine glory, while Tigne Barracks will be dismantled and then rebuilt. This is one of the reasons we have
Conrad Buhagiar on board – he is widely recognised as an expert in the field of conservationist architecture. Besides, the architects will be taking all the necessary advice – for example, when we dismantled the Barracks, Fondazzjoni Wirt Artna had people observing everything we did and all works will continue to be monitored by them.”
So, after nine long years waiting to begin, how soon will the project be completed? “The various phases on both areas of the project are designed to balance restoration work with the more commercial sites. The first part of Tigne Point, facing Valletta, should be ready by 2004 – 2005, while Manoel Island is planned for two phases of five years each. The whole project should be completed within 12 years. However, in the current phase we are ahead of schedule, and now that all the problems have been sorted out, we intend to continue at this pace. For example, during the excavation work, a truckload of rock is removed every four minutes. These are loaded onto barges and taken far out to sea to be deposited at a site specified by the Maritime Authority.”
With three contractors, Polidano Brothers, Vassallo Builders and Gatt Brothers, as shareholders, could this cause problems in the issuing of tenders? “First of all, the three contractors own only 18 per cent of the shares between then, so they are not in a position to influence the outcome of tenders,” replied Alec. “And these shareholders don’t have any advantages over outside contractors for the work. This was made very clear before the project started. All tenders are awarded on merit, and, of course, we want to have as competitive a tendering
situation as possible. Of the two contracts awarded so far, only one was won by a consortium member, but this was totally on merit, and this is the way we will proceed.”
The Manoel Island and Tigne Point project has attracted a fair amount of controversy during the long years the consortium cooled
its heels on the sidelines. Now,
however, the green light has flashed permission for the project to commence, and many are applauding
the fact that the long aband-
oned, derelict buildings
that form so
valuable a part of Malta’s heritage are finally going to be given the attention they deserve. In the meantime, the patient investors are now able to give vent to their enthusiasm. “This project is so different because we are in control of the whole area, and have the possibility to implement a total solution to improve and upgrade the sites,” said Alec in conclusion. “The great attraction is that it is an all-encompassing project in which the whole environment is dependent on the developer too.
“So far, Malta has only really had Valletta as a totally planned area, but this is going to be an entire area
of well-maintained, up-market property, which can be enjoyed by all residents in the surrounding areas, and accessible to everyone.”

  © Standard Publications Limited 1999